ci360™ - One Solution, everyone wins.

ci360™ Solar Kit

How its work Img1

Consistent results
across complex environments

No two projects are the same, but our results are consistent:
Projects delivered with greater speed, control, and confidence.

50-149MW

Franklin PV + Energy Storage

Idaho’s largest solar project built on-time in brutal conditions
25

Weeks

20

Megawatts

0

Available Electrician

Rocky soil, constant rain, 120MW without schedule buffer.

SOLV Energy turned to CI to optimize the eBOS and underground infrastructure for the Franklin PV + BESS project, where rocky soil and persistent wet conditions threatened productivity and schedule certainty.

We worked directly with the EOR to design and fabricate custom, fully integrated underground assemblies, which were further refined by the real-time feedback from onsite field teams during the project build. By minimizing in-field fabrication and simplifying installation, we kept crews moving despite adverse conditions—reducing rework, maintaining safety, and holding the schedule when the environment pushed back.

Franklin PV
Risks Removed
Secret Weapon
Hero Moment

SOLV built Idaho’s largest operating solar facility on-schedule, despite conditions that would’ve derailed other EPC’s timelines

150-299MW

Eldorado 1 Solar Project

Illinois’ agrivoltaics flagship site with an American-made mindset
25

Weeks

20

Megawatts

0

Available Electrician

7 months to build. 150MWac delivered. American innovation.

One of Illinois’ most visible solar projects, Eldorado Solar was layered with an agrivoltaics program, community commitments, and a focus on American-made solutions. Every system onsite had to work right the first time.

As a U.S. manufacturer, CI leveraged its in-house sourcing and procurement teams to integrate domestically-sourced components for its complete product assemblies. 150MW of eBOS solutions were deployed on Eldorado Phase 1 that integrated cleanly into tracker-driven workflows and EPC sequencing, and removed the tariff and schedule volatility of supply chain uncertainty overseas.

Eldorado 1 Solar Project
Risks Removed
Secret Weapon
Hero Moment

Sol Systems energized Eldorado with American made solutions while keeping agrivoitaics commitments and local credibility in-tact (without compromising cost).

300-450MW

Harquahala Sun Solar Projects

Simplifying multiple project phases with thousands of touchpoints
25

Weeks

20

Megawatts

0

Available Electrician

Multi-phased. 450MW. Thousands of touchpoints.

CI was brought in to create eBOS for Harquahala Sun I and II, where phased construction and massive material volume left no margin for missteps in delivery, staging, or installation sequencing.

As part of the ci360™ solution, CI designed, built, and schedule-sequenced PV eBOS kits to align with project developer Copia’s phased completion plan. Assemblies arrived job-ready to eliminate project-to-project bottlenecks and reduce in-field material handling, especially as crews moved from one phase to the next. The result: consistent output, less lost-time handling mass materials, and uninterrupted momentum across a combined 450 MW footprint.

Harquahala Sun Solar Projects
Risks Removed
Secret Weapon
Hero Moment

Copia made its critical completion milestones and developed both phases on schedule, safeguarding a 9-figure investment.

450MW+

Arica + Victory Pass Solar

Energizing neighboring sites with peak skilled labor shortages
25

Weeks

20

Megawatts

0

Available Electrician

Limited labor availability, remote locations, 463 MW combined.

CI was deployed to support the Arica and Victory Pass Solar projects—two neighboring, utility-scale sites where remote desert conditions, long runs, and massive system scale put intense pressure on skilled labor and material availability for the eBOS scope.

Working alongside the EOR, CI developed repetition focused, simplified eBOS assemblies and install kits built for consistent installation regardless of crew experience. With clear Issued for Installation drawings guiding field execution, we reduced installation variability, controlled schedule risk, and enabled delivery at scale without compromising quality.

Arica + Victory Pass Solar
Risks Removed
Secret Weapon
Hero Moment

Clearway energized Arica on-schedule despite a remote site location with constrained material and skilled labor availability

Substation

UPS Regional Hub Substation

The substation timeline that other suppliers turned away
25

Weeks

20

Megawatts

0

Available Electrician

25 weeks. 20 megawatts. 0 available electricians.

CI jumped in to help Hunt Electric complete a high voltage substation for UPS with just 25 weeks to design, fabricate, test, and build. By manufacturing and pre-testing modular substation assemblies in our facility ahead of time, CI was able to provide Hunt with a turnkey solution that shaved weeks off construction and delivered full energization right on schedule, even with a green install crew who’d never worked in high voltage before.

Risks Removed
Secret Weapon
Hero Moment

Hunt Electric built UPS’ substation in record time using just 4 first time crew members who’d never built a substation before

Trusted by those with the highest standards

Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee
Image gallery marquee

What Our Clients Say

What our partners have to say

Build by those
who've build the projects

Construction Innovations was founded by a group of former field electricians, electrical installers, and construction company owners who lived the daily chaos and wasted time on project sites for decades — and decided to do something about it.

We made the solutions we dreamed of in the field.
50-149MW

The Day Job

For the founders who spent their days in the field

Our founders spent decades working on hundreds of electrical projects—running crews, keeping schedules alive, and navigating the chaos that comes when materials, manpower, and design never line up. They weren ’t observing the site challenges from afar. They were living them.

1950 - 2004
150-299MW

The Day Job

For the founders who spent their days in the field

Our founders spent decades working on hundreds of electrical projects—running crews, keeping schedules alive, and navigating the chaos that comes when materials, manpower, and design never line up. They weren ’t observing the site challenges from afar. They were living them.

1950 - 2004
300-499MW

The Day Job

For the founders who spent their days in the field

Our founders spent decades working on hundreds of electrical projects—running crews, keeping schedules alive, and navigating the chaos that comes when materials, manpower, and design never line up. They weren ’t observing the site challenges from afar. They were living them.

1950 - 2004
500+MW

The Day Job

For the founders who spent their days in the field

Our founders spent decades working on hundreds of electrical projects—running crews, keeping schedules alive, and navigating the chaos that comes when materials, manpower, and design never line up. They weren ’t observing the site challenges from afar. They were living them.

1950 - 2004
Substations

The Day Job

For the founders who spent their days in the field

Our founders spent decades working on hundreds of electrical projects—running crews, keeping schedules alive, and navigating the chaos that comes when materials, manpower, and design never line up. They weren ’t observing the site challenges from afar. They were living them.

1950 - 2004
Control Bldg

The Day Job

For the founders who spent their days in the field

Our founders spent decades working on hundreds of electrical projects—running crews, keeping schedules alive, and navigating the chaos that comes when materials, manpower, and design never line up. They weren ’t observing the site challenges from afar. They were living them.

1950 - 2004

Factory-integrated, turnkey solutions for
Solar Power Data Centers Conventional Energy